CRANGAN BAY | Stage 6 - Under Civil Construction
Current Update: May 2026
Over in Stage 6, works are well underway with bulk earthworks progressing and initial lot shaping and road preparation in motion. Sewer installation has also commenced, marking another important step forward in the expansion of our community. Further registration updates on this stage will be provided to our stage 6 buyers as we enter into 2027.
Registration timeframes again remain on track expected for Mid 2027. Civil Construction ETA completion Mid 2027.
Titles estimated: Mid 2027
|
Planning |
100% |
|
Planning |
100%
|
|
Civil Construction |
15% Complete |
|
Site Establishment Bulk Earthworks Drainage Works Sewer Works Water Reticulation Electrical & NBN Footpaths/Asphalt/Linemarking Practical Completion
|
100% 90% 0% 0% 0% 0% 0% 0%
|
|
Registration Progress |
0% |
|
Statement of Compliance Lodge Plan of Subdivision Titles |
0% 0% 0%
|