CRANGAN BAY | Stage 6 - Under Civil Construction

Current Update: May 2026

Over in Stage 6, works are well underway with bulk earthworks progressing and initial lot shaping and road preparation in motion. Sewer installation has also commenced, marking another important step forward in the expansion of our community. Further registration updates on this stage will be provided to our stage 6 buyers as we enter into 2027. 

Registration timeframes again remain on track expected for Mid 2027. Civil Construction ETA completion Mid 2027.

Titles estimated: Mid 2027              

Planning

100%

Planning

100%

 

Civil Construction   

15% Complete

Site Establishment                             

Bulk Earthworks                                

Drainage Works                                 

Sewer Works                                     

Water Reticulation                            

Electrical & NBN                                

Footpaths/Asphalt/Linemarking         

Practical Completion                          

 

100%

90%

0%

0%

0%

0%

0%

0%

 

Registration Progress         

0% 

Statement of Compliance      

Lodge Plan of Subdivision                 

Titles   

0%

0%

0%

 

 